TRITEC Building Company completed the 7,600 sq. ft. build-out of Arooga's Grille House & Sports Bar at 1 West Main Street in Patchogue, NY, in August 2016. The restaurant is part of New Village at Patchogue, the mixed-use community TRITEC developed and built in the heart of downtown. The full-service restaurant and sports bar has a 50-seat bar with 47 beers on tap, 101 televisions, six ceiling-mounted subwoofers and a commercial kitchen with high-end ovens and fryers. Two six-foot bifold doors open the bar to sidewalk seating on Main Street. Mancini Architects designed the space.
Building a high-energy restaurant beneath occupied apartments took careful planning. The space sits on a post-tensioned concrete slab, so TRITEC X-rayed it to locate the tendons before making any penetrations and rerouted plumbing waste lines where they conflicted. A 10-inch level change between the bar and dining area became a ramp. A three-inch change through the kitchen was too heavy for lightweight concrete on the slab, so the team built it up with two-inch wood sleepers, foam, plywood and a self-leveling topping instead.
To keep equipment off the residences, TRITEC used split HVAC systems and ran eight line sets and their electrical service four floors up an existing shaft to the roof. The ceiling has 1½ inches of sound insulation, and the kitchen hood connects to an air-scrubbing system so cooking odors don't reach the apartments. Bar waste piping that runs below the slab through the parking garage is heat-traced and insulated, and the fryer-oil tanks fill and empty through an exterior wall connection, so oil never travels through the dining room.
With residents already living upstairs, work was limited to normal business hours, with no nights or weekends. One week before opening, a car crashed into the space and damaged finished work. TRITEC's subcontractors rebuilt the damaged areas immediately, and the restaurant opened just two weeks past its original date.
TRITEC Building Company built the 7,600 sq. ft. restaurant and sports bar at New Village at Patchogue, completed in August 2016.
With split HVAC systems run to the roof, ceiling sound insulation, an odor-scrubbing kitchen exhaust and work kept to business hours.
The restaurant sits on a post-tensioned slab, so TRITEC X-rayed it before every penetration and used a lightweight floor build-up to avoid overloading it.
Yes, including Arooga's and Primo Locale at New Village and the restaurant tenants at Station Yards.